284 Copyright © Acronis, Inc., 2000-2010
Edit a plan/tas k
Click
Backup plan
Edit.
Backup plan editing is performed in the same way as crea tion (p. 181), except for
the following limitations:
It is not always possible to change backup scheme properties if the created
archive is not empty (i.e. contains backups).
1. It is not possible to change the scheme to Grandfather-Father-Son or Tower of
Hanoi.
2. If the Tower of Hanoi scheme is used, it is not possible to change the number
of l evels .
In all other cases the scheme ca n be changed, and should continue to operate as
i f the exi s ting archi ves were created by a new scheme. For emp ty archi ves all
changes are possible.
Why can't I edit the backup plan?
The backup plan is currently running.
Editing of the currently running backup plan is impossible.
The backup plan has a centralized origin.
Direct editing of centralized backup plans is not possible. You need to edit the
original backup policy.
Click
Task
Edit.
Why can't I edit the task?
Task belongs to a backup plan
Only tasks that do not belong to a backup plan, such as a recovery task, can
be modified by direct editing. When you need to modify a task belonging to a
local backup plan, edit the backup plan. A task belonging to a centralized
backup plan can be modified by editing the centralized policy that spawned
the plan.
Del ete a pl an/task
Click
Backup plan
Delete.
What will happen if I delete the backup plan?
The plan's deletion deletes all its tasks.
Why can't I delete the backup plan?
The backup plan is in the "Running" state
A backup plan cannot be deleted, if at least one of its tasks is running.
The backup plan has a centralized origin.
A centralized plan can be deleted by the management server administrator
by revoking the backup policy that produced the plan.
Click
Task
Delete.